Construction of 52 pillars on the spillway of Polavaram project over
For the spillway bridge, the company had completed laying of 45 slabs while the work on laying three more slabs are nearing completion
Vijayawada: The construction of 52 pillars of 52-metre-high on the spillway of Polavaram irrigation project was completed, said Megha Engineering and Infrastructures Limited.
The company, which has taken up the execution of Polavaram project, said that they had completed the construction of 52 pillars at a height of 52 meters each on the spillway by Thursday and claimed that their works were hindered in the last year due to heavy rains and floods and outbreak of Covid-19 pandemic.[Readmore]